Newsletter 2009
November Newsletter 2009
After a 15 month suspension (due to the delay outlined in October) there is an enormous clean up operation taking place within the site and within each individual unit in preparation for finishing trades of the southside of the development. Buildings are being re-scaffolded and machinery, cranes etc re-mobilized. Tiling of roofs and internal tiling has re-commenced and in some units already completed. Windows and doors are in production for delivery early 2010. The first swimming pool has also been excavated...
October Newsletter 2009
The estimated completion date for the development is March 2011; however this date has not been formally confirmed by the Contractor. The company is currently in negotiations with the Contractor and would hope to be in a position to confirm the completion schedule in the coming weeks...